The Abyss, Measured: 27 Months of Saanich Suite Permits

Last summer I asked whether your building permit application was languishing in an eternal abyss. I had 22 approved permits to go on. Twenty-two is a pretty small dataset.

This time I have 454 applications. Every garden suite, secondary suite and houseplex application submitted to the District of Saanich between 01 July 2024 — the day the Province’s Small-Scale Multi-Unit Housing (SSMUH) rules took effect — and 30 September 2026. Twenty-seven months. By 02 October 2026, 273 of them had a permit in hand.

Some of what I wrote last year holds up. One headline finding does not. And the abyss turns out to be deeper than the tracker’s own numbers suggest.

The Data

Saanich’s Permit and Development Tracker holds a detail page for every building permit. I read all of them in the BLD and RBP series — roughly 2,250 pages — on 02 October 2026. Of those, 1,380 were applied for between 01 July 2024 and 30 September 2026. The 454 whose stated purpose describes a garden suite, secondary suite or houseplex are the subject of this article.

Housing TypeApplicationsPermit IssuedStill OpenCancelled or expiredPercentage of Permits Issued
Secondary Suite195132451868%
Garden Suite916220968%
Houseplex16879791047%
Total4542732733760%

Table 1: Status on 02 October 2026 of the 454 garden suite, secondary suite and houseplex applications made to Saanich between 01 July 2024 and 30 September 2026, by housing type.

Permit issued” here means the tracker shows the file at Permit Ready for Issuance, Permit Issued or Final. The four charts that follow use only those 273 permits. Keep that in mind — I’ll come back to the other 181.

Each detail page carries a small pie chart of “Active Processing Days”: days With District and days With Applicant. Those are the two numbers behind every figure here. There is one catch. Saanich doesn’t say what kind of day it’s counting, so I checked. For the 264 issued permits with an issue date, I counted the weekdays between application and issuance. That count matched the tracker within 5 days for 59% of permits, and within 15 days for 97%. Calendar days missed by about 48 days at the median.

The tracker counts working days. Multiply by roughly 1.4 to get the calendar time you actually live through. Put another way, 20 working days is about one calendar month — the conversion I use from here on.

Figure 1  Total active processing days (With District + With Applicant) for the 273 issued permits, stacked by housing type. Each bin is 20 working days — about one calendar month.

How Long Does It Take?

The median issued permit took 111 working days — a little over five calendar months. The average was 124 working days, about six. The mean sits above the median because the right tail is long: 52 permits (19%) took more than 180 working days, roughly nine calendar months or more.

Stacking by type shows the total is really three distributions laid on top of each other. Secondary suites pile up early. Their busiest bin is 41–60 working days, and 94 of 132 (71%) were issued within 100. Houseplexes start late and spread wide. Not one was issued within 60 working days, only 8 of 79 within 100, and 51 (65%) took longer than 140.

Garden suites sit in between — about what you’d expect from a building that’s more than a suite and less than a fourplex. The second hump in the total, at 121–140 days, is where all three overlap: 11 secondary suites, 10 garden suites, 12 houseplexes.

The fastest permit in the set took 15 working days — a homeowner’s secondary suite applied for in August 2026: 12 days with the District, 3 with the applicant. Last year’s fastest was 33 days.

Last year’s slowest approval was 105 days. In this larger set, 105 working days is just under the median. That isn’t because Saanich got slower. It’s because last year’s sample could only contain permits that finished quickly. I’ll return to that, too.

Figure 2: Each dot is one issued permit. Horizontal axis: working days waiting for the District to act. Vertical axis: working days waiting for the applicant to act. The ✕ marks the average (50, 74); the ◆ marks the median (44, 57).  The red lines mark the area shown in Figures 3 and 4: up to 150 working days with the District and 300 with the applicant. Only five permits fall outside it — three above, two to the right.

Whose Desk Is It On?

Both markers sit above the diagonal. The average permit spent 50 working days waiting on Saanich and 74 waiting on the applicant. Roughly three days in five, the file was on the applicant’s desk — not the District’s.

The spread is lopsided, too. Along the District axis, the dots are bunched: half the permits spent 44 days or fewer there, and only 14 of 273 went past 100. Up the applicant axis they scatter much higher — 14 permits spent more than 200 working days (ten-plus calendar months) waiting on the applicant. The longest District wait was 234 days. The longest applicant wait was 418. (One file reports 535, but most of that is revision work done after its permit was issued in November 2024. Counted only to issuance, it took about 81 working days — 45 with the District, 36 with the applicant.)

Last year I noted that no application had spent more than 60 days on the City’s desk. With 27 months of data, that’s no longer true — 70 issued permits, about a quarter, passed 60 District days. But the main shape hasn’t changed. When a permit drags, it is usually waiting for the person who applied for it.

Figure 3: The same 273 permits, coloured by housing type: garden suite (62), houseplex (79), secondary suite (132). ✕ = average and ◆ = median for each type. Five outliers fall outside the axes; they are included in the averages and medians.  The scatter plot shows only the area inside the red lines in Figure 2. The five permits outside it aren’t plotted, but are included in the averages and medians.

Houseplexes Are a Different Animal

The secondary-suite median sits right on the diagonal: 34 days with the District, 34 with the applicant. For houseplexes, 73% of issued permits spent more time with the applicant than with Saanich. And those are the ones that finished. Of the 168 houseplex applications, only 79 — 47% — had a permit by 02 October 2026. Both suite types were at 68%.

Issued PermitsCountMedian Days
with District
Median Days
with Applicant
Median
Total Days
Secondary Suite132343475
Garden Suite624557105
Houseplex796597151

Table 2: Median working days with the District, with the applicant, and in total for the 273 issued permits, by housing type.

That’s not surprising when you think about what a houseplex is. Three or four dwellings instead of one or two. Fire separation between units. Servicing that a single basement suite never touches. More drawings means more for the District to review, and more for the applicant to revise. The data can’t tell me which of those steps eats the time. It does tell me where to look.

Figure 4:  The same 273 permits, coloured by who the tracker lists as applicant: homeowner (55), agent (33), professional (67) or unknown (118). ✕ = average and ◆ = median for each group. Five outliers fall outside the axes; they are included in the averages and medians  The axes show only the area inside the red lines in Figure 2. The five permits outside it aren’t plotted, but are included in the averages and medians.

Homeowner or Professional? Retesting Last Year’s Claim

Last year’s headline was that homeowners beat professionals. The average homeowner permit took 52 days; the average professional permit took 73 (40% longer). I built an argument about old habits on that gap.  With 27 months of data, the gap is gone.

Issued PermitsCountMedian Days
with District
Median Days
with Applicant
Median
Total Days
Homeowner554581132
Professional674581136
Agent334777120

Table 3:  Median working days with the District, with the applicant, and in total, by applicant type. Covers the 155 issued permits whose applicant is identified on the tracker; the 118 “unknown” permits are excluded.

Homeowner and professional medians are identical on both axes: 45 days with the District, 81 with the applicant. Their averages differ by three days or less. Splitting by housing type doesn’t rescue the old claim either. Professionals were faster on secondary suites (median 75 vs 86 days). Homeowners were faster on houseplexes (172 vs 189). Garden suites favoured homeowners, but on six homeowner permits I won’t lean on that. No consistent winner.

“Agent” is what the tracker prints when someone files on the owner’s behalf without being named. It could be a designer, a contractor or a relative. Their numbers sit with everyone else’s.

Then there is the grey cloud: 118 permits marked “unknown”. It’s tempting to read their low centroid (45, 48) as a fourth kind of applicant who knows something the others don’t. It isn’t. Saanich hides contact details once a file is archived, and 117 of these 118 are archived files. Files appear to be archived once they’re closed out, which favours older applications that moved quickly — 99 of the 118 were applied for before July 2025. “Unknown” is a filing status, not an applicant type. It belongs in the chart so every permit is accounted for, but it shouldn’t be compared with the other three.

The Permits That Aren’t in the Charts

Every chart above shows permits that made it. On 02 October 2026, another 144 applications were still in process. They are the reason the charts flatter the system.

Of those 144, 103 were waiting on the applicant to provide more information. The other 41 were with the District, most of them in referrals. The median open file had already logged 123 working days. Sixty-eight of them had passed the 124-day average of the issued permits, and 41 had passed 200 days. None of that appears in Figures 1 through 4.

This is the same trap my 2025 article fell into, only worse. That study looked at applications from January to April 2025 that were approved by 14 June 2025. By construction, only fast permits could be in it. The 52- and 73-day averages were the quick end of the distribution, not the middle of it.

There is a standard fix. A Kaplan–Meier estimate uses every application — issued ones for their finish time, open ones for the time they’ve survived so far — to estimate how long the typical application will take. Applied to all 454:

All Applications
(Kaplan-Meier estimate)
ApplicationsMedian Working
Days to Issuance
Roughly, in calendar months
Secondary Suite195944 3/4
Garden Suite911266 1/4
Houseplex16820010
Al Three Types4541477 1/2

Table 4:  Estimated median working days from application to permit issuance for all 454 applications, by housing type. The Kaplan–Meier estimate counts the 144 open applications for the time they’ve been in process so far. Calendar months use 20 working days ≈ 1 month.

The honest answer to “how long will my permit take?” is about 147 working days, not 111. Call it seven and a half calendar months. For a houseplex, ten. One in four applications is estimated to take longer than 287 working days — about 14 calendar months.

Is it getting better? Possibly. The estimated median was 133 working days for applications filed in the second half of 2024, 190 for the first half of 2025, and 185 for the second half. For the first half of 2026 it drops to 120. I’d treat that last number as encouraging rather than proven — those applications have had at most nine months to resolve, and the slow ones haven’t shown themselves yet.

Limitations

This dataset has more than four times as many applications as last year’s and spans more than two years. It is still one municipality, and it is still the tracker’s version of events.

  • The unit of time is inferred. Saanich doesn’t define “Active Processing Days”. The weekday match is strong but not perfect — statutory holidays alone would explain a few days’ gap.
  • Classification is by keyword. A permit counts if its stated purpose names a garden suite, secondary suite or houseplex. Six were included on judgment, and Saanich has rewritten some descriptions since my 2025 pull.
  • Applicant type is only as good as the tracker’s label. “Professional” means a named company or person; “agent” means the tracker said agent. Over two-fifths of issued permits have no visible applicant at all.
  • The four figures show issued permits only. The Kaplan–Meier estimates use all 454, but treat cancelled and expired files as if they simply stopped being observed. If those were disproportionately slow files, the true medians are a little higher still.
  • The tracker counts time on each desk, not the number of round trips. Last year I counted how many times each application was sent back. This dataset doesn’t include that, so I can’t say whether delay comes from many short revisions or a few long ones.

What Could Be Behind the Data?

Last year I closed with a section called “Old Habits Die Hard”. Professionals, I suggested, were carrying decades of pre-SSMUH experience into a process that no longer rewarded it. Homeowners, with nothing to unlearn, read the guidance and sailed through.

The larger dataset doesn’t support that. Either the homeowner advantage was never real — 22 fast survivors is a thin foundation — or professionals have since caught up. I can’t separate those two explanations. I can say the gap isn’t there now.

What the data does support is less flattering to everyone. The permit spends most of its life waiting on the applicant. That’s true for homeowners and professionals alike, and it’s most true for houseplexes. Saanich’s guidance materials for SSMUH are thorough. The District’s median review time on a secondary suite is 34 working days. The bigger lever is on the other side of the counter: a package complete enough that it doesn’t come back, and a fast, complete answer when it does.

That changes what I’d tell someone about to apply. It matters less who fills in the form. It matters a great deal what you’re building. A secondary suite and a fourplex are not the same application with a different unit count. Budget your time accordingly — and if it’s a houseplex, assume ten months, not five.

I’ve built secondary suites, and I’ve now read every SSMUH permit file Saanich has opened since the rules changed. If you’re planning a suite or a houseplex and want the package right before it goes in, call or email to set up a consultation.

The abyss is real, but it isn’t eternal. Most of it is on our side of the desk. So here is my question for applicants who got through quickly: what did you have in your first submission that everyone else was missing?